Drive West Lucas Road between Angel Parkway and Country Club Road this week and you will see survey crews and fresh utility-locate marks along the shoulders. You will not see new pavement yet. This early work is the first visible part of the West Lucas Road Reconstruction and Widening, the largest roadway project the City of Lucas has ever paid for.
Residents who use the road every day will care most about how the contract is built. The job is split into seven traffic-control phases, and the bid documents spell out what has to stay open while each one is underway. You will follow it as a series of moving work zones, with each one announced as it comes.
Survey Marks First, Pavement Later
On October 21, 2026, the City of Lucas posted a construction update with a tentative start date:
"Construction on the West Lucas Road Widening Project is expected to begin soon, with construction and excavation activities tentatively scheduled to begin Monday, October 26, 2026."
The same notice said the date could change "based on project conditions and scheduling." The City's November Lucas Leader newsletter gave a more detailed update. Surveying, utility locates and other site preparation were underway "to identify potential conflicts before construction begins," and "full roadway construction has not yet begun." October 26 turned out to be the start of the preparation work. Full roadway construction had not started as of that newsletter.
That prep work explains the marks along the shoulders. Before heavy equipment touches the road, the contractor has to find every buried line in the right-of-way. The project includes utility relocations and about 6,000 linear feet of new 8-inch sewer force main. The City has said it will post timelines, traffic impacts, closures and detours on lucastexas.us once the construction schedule is final.
Seven Phases, With School and Church Access Built In
The engineering scope approved with the project describes "a traffic control plan sequence consisting of 7 phases of work." Each phase moves traffic to a new pattern while crews rebuild another section. For a corridor with schools, churches and businesses fronting the road, the phasing is how access is protected.
The contract is specific about the busiest driveways on the corridor. A bid addendum issued in July 2026 says that "two driveways must remain open at all times when constructing Lovejoy Independent School District Entrance/Exit Driveways." The open driveways may be temporary, but they have to provide all-weather access. The cost of that temporary access falls on the contractor as part of traffic handling, so it is already priced into the job.
The bid also lists the signs that will be taken down and put back up as the road is widened. They include signs for:
- A Painting Place
- Trinity Tabernacle
- Cornerstone Church
- Two "Student Drop-Off/Pick-up/Staff/Faculty Parking" signs
These signs are being relocated, not removed. During the work, the places they point to stay on West Lucas Road, and their signs move with the new right-of-way. If you head to Sunday service, an art class or school pickup along this stretch, a sign may be in a slightly different spot from week to week, but it is still there.
What $19.5 Million Buys on One Road
Lucas City Council approved the construction contract unanimously, 6–0, on August 6, 2026. The council minutes break down the total:
| Component | Amount |
|---|---|
| Tiseo Paving Company contract, not to exceed | $17,996,144.60 |
| Contingency | $969,159.77 |
| Right-of-way acquisition | $500,000 |
| Total authorized, as stated in the minutes | $19,465,305 |
The three components add up to $19,465,304.37. The council's motion rounds that to the whole-dollar figure shown.
Of that total, the City set aside $17,939,549 for the West Lucas Road account and $1,525,756 for the 8-inch force main relocation. About $1.5 million of the money goes to underground sewer infrastructure that drivers will never see.
The road itself is designed to last. The scope calls for 10-inch reinforced concrete pavement on 8 inches of lime-stabilized subgrade, along with pedestrian sidewalks. The bid tabulation includes 6,515 square yards of 4-inch concrete sidewalk. For people who walk or jog near home, that means a dedicated walking surface along a road that is currently built only for cars.
Mayor Dusty Kuykendall wrote in the November Lucas Leader that the project is "the largest roadway investment in our City's history," and that "through careful financial planning, the project is fully funded without taking on debt or requiring a tax increase to fund the project." In the same letter he said the City remains "focused on improving safety and mobility while protecting the rural character that makes Lucas special."
Paying cash also shapes the schedule. Lucas is not waiting on a future bond sale, so the timing depends on the construction phases rather than on financing.
A County Project the City Took On Itself
The corridor has been on regional plans for years. Collin County's FY 2022 capital improvement book listed a 2018 bond project for Lucas Road from FM 2551/Angel Parkway to FM 1378/Country Club Road, with a start date of 2020. The same entry says the project "has been cancelled and funding no longer needed."
The City then went ahead with its own project. BCC Engineering is the engineer of record. Freese and Nichols, Inc. was hired to manage the bid and construction phases. The City published the bid as Bid 045-026 on May 15, 2026, and opened bids on July 21. At that opening, Tiseo Paving Company's bid of $17,996,144.60 listed a duration of 720 calendar days, roughly two years of work.
Two years of work spread over seven phases means each pattern of cones and lane shifts will last a while. A detour you learn in January may give way to a different one later in the year.
Keeping Up While the Cones Move
The City's own channels will have the phase announcements first. Some practical ways to stay ahead of them:
- Sign up for "Notify Me" alerts. The City offers Notify Me® subscriptions on lucastexas.us, including alerts for Lucas News posts. You can manage them through a website account.
- Watch the City Council meetings. One is set for Thursday, November 19, at 6:30 p.m. at Lucas City Hall, 665 Country Club Road.
- Read the monthly Lucas Leader. The November issue reported that site preparation was underway, and the newsletter is where the City has been recapping the project.
- Allow extra time near school and church driveways. Access is protected there, but temporary driveways and relocated signs take a moment to find the first time.
The City has asked motorists "to use extra caution when traveling through the area and remain alert for crews, equipment, and changing roadway conditions."
The holiday calendar keeps going alongside the construction. Lucas City Hall on Country Club Road is collecting tags from its holiday Giving Tree, with new, unwrapped gifts due back by December 11, 2026. Country Christmas runs Friday, December 4, from 6 to 9 p.m. at Lucas Community Park. For a fuller picture of how traffic moves through town, our earlier look at the Lucas traffic chokepoint covers the routes residents already use, and our Lucas neighborhood page gathers what we have written about the town.